October 29, 2026
On the Coast Highway 101 bridge over the San Elijo Lagoon inlet, walkers favor the west walkway, the one with the ocean views, according to the San Diego Union-Tribune. It is also narrower than the walkway on the east side.
Over the next several years, Encinitas will rebuild the south end of Cardiff's Coast Highway one piece at a time. The bridge has federal repair funding and is now in design. A new crossing at the Solana Beach line got its design on Oct. 21. City staff say the finished road will feel like one corridor. Still, the stretch most walkers choose, the ocean side of the bridge, falls into a budget category the grant doesn't cover. Whether it gets wider comes down to whether the city pays for it.
The bridge is older than most of the town around it. A March 2026 city staff report says it was built in 1934 and widened on its western side in 1953. It is a 200-foot reinforced concrete pile bridge with four travel lanes, a protected bike lane in each direction, and an ADA-compliant sidewalk on the east side.
So the accessible, wider walkway is the east one, which faces the lagoon. The west walkway faces the ocean and gets more foot traffic. The bridge sits just south of the San Elijo State Beach campground, and every pedestrian and cyclist going between the campground side and the lagoon mouth crosses it.
It has been patched before. The city report lists pier repairs in the 1990s and emergency work in 2019 to patch areas of concrete delamination on the underside of the deck. It also notes that Caltrans structural engineers inspect the bridge regularly, most recently in 2024.
In January, the City Council awarded Kleinfelder, Inc. a $270,000 contract to evaluate all 46 of the city's bridges and write a 10-year repair plan. The results came back in September. Two structures were rated poor. One is this bridge. The other is a pedestrian bridge over a drainage swale at Leucadia Oaks Park.
The lagoon bridge is "showing signs of deterioration," including chipped concrete and rusting rebar, the Union-Tribune reported. Kleinfelder engineer Kelly Burnell told the council that "poor doesn't mean unsafe." It means the bridge needs repair work.
The Coast News called it the city's "most significant structural concern" in an assessment that proposed about $5.9 million in repairs over 10 years. The paper quoted the engineer describing the bridge as "in a rough spot with the tide running right under it."
The poor rating also makes the bridge eligible for a Federal Highway Administration funding program, and that eligibility sets the terms for everything that follows.
The city's grant fact sheet, updated in July 2026, lists a $17.08 million Highway Bridge Program award for the project, with an 11.47% local match. The Union-Tribune put the city's share of the repairs at about $3.5 million.
That money pays for repair. City Engineering Director Dan Nutter told the council that major improvements count as "betterment," and that Encinitas would pay the full cost of those. The example the paper gave was widening the narrow pedestrian walkway. Before any of that is settled, the city has to agree with Caltrans on which items count as which.
"This is an arduous process," Nutter said, according to the Union-Tribune, adding that construction could be about five years away. Councilmember Joy Lyndes, who represents Cardiff, said residents will want betterments given how many pedestrians and cyclists cross the bridge every day. She argued for doing them alongside the repairs: "We're probably never going to have a better opportunity."
The design work has started, but only a small piece of it. On March 11, 2026, the council approved a $199,817 contract with Dokken Engineering. Six firms had submitted proposals. Only $200,000 in design funding had been authorized at that point, so the first task is limited to agency and utility coordination, a design survey, field review, and concept exhibits for Caltrans to approve the grant scope. That first phase was expected to take about six months. Staff will return to the council once the remaining $1,936,000 in design funding is authorized, and the city expects full design and permitting to take four years.
The concept exhibits going to Caltrans are where the line between repair and betterment gets drawn. The width of the west walkway depends on which side of that line it lands on.
The other project is closer to happening. On Oct. 21, the council chose a design for the stretch of South Coast Highway 101 at the Solana Beach border. The City of Encinitas Council Rundown describes Option 2A this way:
The Coast News added more detail. The bike lanes would be 6 feet wide with painted buffers instead of physical barriers, and the travel lanes would be 10 or 10.5 feet. A version with a full traffic signal failed 2-3, with Councilmember Luke Shaffer and Mayor Bruce Ehlers voting for it. The version with smaller Type 1-A signal poles passed 3-2, with Deputy Mayor Jim O'Hara and Councilmembers Marco San Antonio and Joy Lyndes in favor.
The signal location follows the path people already take. "Crossings of Highway 101 at Harbaugh Trails have been happening for decades, and we know exactly why," Solana Beach City Manager Alyssa Muto told the paper. She called the chosen option "a step in the right direction." O'Hara praised the plan for removing the curb stops and bollards: "It actually makes the road much safer."
This crossing has its own small grant. Encinitas accepted a $349,920 state-administered HSIP grant in November 2025, and Caltrans has to approve the scope changes. Lyndes noted that the grants cover only the stretch from Las Olas to the Solana Beach crossing, which she said limits how big the city can think right now. Next, staff will coordinate with Solana Beach, ask Caltrans to approve the scope changes, refine the design, and bring it back to the council. The city's recap of the vote gives no dates for those steps.
So the south end of the corridor now has a 14-foot west-side path on paper, while the bridge to the north still has a west walkway narrow enough that widening it is a line item the city would pay for alone. Nutter addressed the gap between them at the same meeting:
"Whatever the bridge rehabilitation needs would be, we would ensure at the end of the day that we have a consistent corridor from Chesterfield to the Solana Beach border."
None of this changes your walk yet. Here is the stretch as it works today, with what is planned for each part:
The water under the bridge is the reason the bridge matters, and you can spend time with it this season. In an Oct. 9 update, Nature Collective reported that it is taking weekly water samples and collecting continuous-monitor data, and that restored tidal exchange improves the lagoon's water clarity.
Coming up on the calendar:
Questions about how public projects like the lagoon bridge or the Harbaugh crossing could affect a home along this stretch often come up when a family starts planning a move or settling an estate. Chintz Team follows these coastal projects closely, and we're happy to walk you through what is known and what is still being decided. Request a free home valuation and senior transition consultation whenever the timing feels right for you.
Stay up to date on the latest real estate trends.
AS A SENIOR REAL ESTATE SPECIALIST (SRES) WE ARE COMMITTED TO MEETING THE REAL ESTATE NEEDS OF SENIORS AND THEIR FAMILY MEMBERS. WE HAVE THE TRAINING AND CREDENTIALS NECESSARY TO COUNSEL 50+ CLIENTS AND THEIR FAMILIES THROUGH MAJOR FINANCIAL AND LIFESTYLE TRANSITIONS INVOLVED IN RELOCATING, REFINANCING OR SELLING THEIR FAMILY HOME.